Risers can be easily overlooked in construction projects. They’re tucked away behind walls and ceilings and often treated as a late-stage detail rather than a fundamental part of the construction process.
When builders don’t coordinate MEP routes, structural supports and riser floors at the outset of a project, it results in unnecessary rework, delays and additional labour.
Early BIM-led coordination and a flexible riser design approach can reduce waste and improve productivity across cost, coordination and delivery.
The hidden cost of late coordination
Late riser coordination often proceeds like this: structural openings are created, services are routed through the building, and the riser floor is designed or adapted around the space left.
This sequence is problematic: MEP routes can clash with structural supports, access can be compromised, and installers can end up fitting services into a void which was never intended to be there.
The consequences include more drilling, new supports, alterations to the ducting/piping and time lost waiting for decisions.
Mace Construct’s Build Smart, Build Better report points to coordination issues, rework, waiting for materials and unnecessary movement around the site as the main causes of productivity loss.
3 Pressures on Your Project
- Cost: Late changes, duplicated work, extra labour and remedial works all add cost. A riser modified on site can quickly become more expensive than one properly coordinated from the outset.
- Programme: The riser works sit somewhere between structural and MEP installation. If the services can’t be installed as planned, subsequent trades can be impacted and the wider programme can be affected.
- Risk: Open riser voids present a safety issue, and clashes between services and supports can lead to ad hoc solutions, quality issues and an increased burden on on-site coordination.
The Rework Challenge
The Mace report cites the Get It Right Initiative’s estimate that errors and rework cost the construction industry about 20p for every £1 of output. On complex projects where services, structure and finishes must come together in confined spaces, rework risk is high.
Digital coordination is one of the most tangible ways of achieving this. Mace’s findings showed that digitally mature projects retained around £1m more of their forecast margin than less digitally mature, similar-sized projects of the same building type. The report identifies clash detection and 3D coordination as two digital applications making the most practical difference on site.
That’s where riser coordination becomes important.
How Comtec Coordinates
Coordination is typically achieved through 3D BIM modelling. MEP engineers place their pipes and ducts in line with Comtec’s Riser Design Guidelines, and our design team finalises the positions of GRP joists and support beams around those services to ensure no overlaps or clashes.
Rather than treating riser floors as elements that come later, Comtec models the riser within the BIM model as the project progresses. This enables MEP routes, structural supports, GRP joists and service penetrations to be coordinated in one place.
By involving Comtec early, project teams can align structural and MEP requirements when changes are still relatively straightforward.
Riser Systems at Comtec
Early coordination doesn’t mean you’ve locked everything down before the design is complete. The MEP requirements can change as the project progresses.
Comtec’s AlphaRiser is designed with this in mind. Its GRP joists can be easily adjusted to accommodate the location of MEP services, allowing the riser solution to be installed early in the programme while retaining flexibility for MEP coordination.
The system provides a simple, adjustable way to position and fix MEP services. Once MEP works commence, penetrations can be marked up and cut out through the lightweight GRP grating to allow services to pass through.
This combines early BIM coordination with a flexible installation approach. Project teams benefit from a coordinated design strategy while still adapting to design development.
Comtec’s integrated riser management brings design, manufacture and construction knowledge together to eliminate avoidable waste, avoid duplication of work and reduce coordination time.
Risers can have a big impact on a project. The issue isn’t whether the builder’s riser work will affect cost, programme and risk. The question is whether your project will manage those impacts proactively or pay for them later.